IOCL Paradip Loading Arms

Installation of supplies from SVT Germany.

IOCL Paradip
 
IOCL Paradip
 
IOCL Paradip
 

IOCL Marketing

IOCL Marketing Head Office – Order for 128 Aluminum Geodesic dome roofs placed on BTE, Australia and Empire Industrial Equipment, Mumbai on March 31, 2013.

Complexity involved and Highlights of execution:

  • All the tanks were in existing IOCL Oil Terminals, where there were regular operations.
  • Dome roofs had to be erected and commissioned at each location, within prescribed time, after obtaining shut downs as these were on-going operational terminals.
  • Dome roofs were in various sizes - dia starting from 8 metres and going up to 24 metres.
  • There were 54 locations all over India.
  • Simultaneous work at nearly twenty locations had to be managed by engaging as many teams.
  • Erection involved the use of special tools and tackles.
IOCL
 
IOCL
 

What you see are a couple of pictures of how the erections were carried out. While the job was completed to the satisfaction of the customer; there were some IOCL offices who expressed appreciation and commendation for the extra-ordinary work done.

Certificate:

Here's the certificate received from IOCL on successful completion of this major project

View
IOCL


MSEDCL T&D Revamp

Maharashtra State Electricity Distribution Company Ltd. Thane III T&D Capital & revamp project

In year 2013, Empire Industrial Equipment executed a major T&D Job which includes Capital, Renovation & Modernisation works. MSEDCL had contracted with Supreme Infrastructure (I) Ltd. for new & revamping of the existing distribution network at several places in Mumbai. Supreme had offloaded the work to us for the Mumbra, Diva, Shilphata / Kalyanphata, Khidkali, Dahisar and Navi Mumbai (Mahape) areas – some of the most congested localities in Mumbai.

The job posed several changes, as it involved Supply, erection, testing & commissioning of various activities as below under shut-down conditions; respecting right of way of existing traffic and local population priorities.

MSEDCL
 
Projects Completed
Projects Completed
  1. New HT 22kV, LT Overhead Lines & Underground Cables.

  2. New 22kV Switching Station Indoor type.

  3. New 8 Way, 6 Way, 4 Way & Mini Feeder Pillars.

  4. Removal of the existing 22 KV lines, 22kV Isolators without EB, 22KV DO Set.

  5. Replacement of HT & LT RSJ poles, conductors & underground cables, upgrading them, Conversion of Overhead lines to Underground cables.

  6. Installation of New Distribution Transformers Centres (DTCs) of various capacities, upgrading DTCs capacity.

  7. Laying power and control cables, terminations thereof and commissioning.

 

Oil India Crude Engine Genset

OIL PS4 and PS8 Installation of Shengli Crude Engine Generator

We have successfully completed installation and commissioning of 2 numbers Crude Engine Generators at Oil India Limited Pumping Station 4 (PS4) in Sekoni, Assam in January 2018.

Likewise the installation of Pumping Station 8 (PS8) at Sonapur, West Bengal is complete. The commissioning is in progress and is likely to be completed by March 18.

The job included civil works like CEG foundations, mechanical works like crude engine pipeline, besides the installation of CEGs themselves and the connected electrical work like cabling and electrical panel.

Oil India Crude Oil DG set

Rourkela Additional Heat Treatment Facility

On the 7th April 2016, EIE along with CAN-ENGG, Canada commissioned the Additional Heat Treatment Facility at the Rourkela Plant of SAIL. The facility enables RSP to produce toughened steel for India - steel that can even withstand heavy shelling/bombardment. Here's a look at the commissioned plant.

The entire job from concept design to commissioning was executed by EIE team in a period of 24 months. The video captures the entire sequence of operations.

Rourkela
Rourkela
Rourkela

Mooring Winches Installation Petronet LNG Dahej

EPC project for Constant Tension Mooring Winches Installation Petronet LNG Dahej, Gujarat - supplies from Bodewes, Netherlands.

 Mooring Winches Installation Petronet
 
 Mooring Winches Installation Petronet
 

BINA Refinery Zimmerman Unheading Valve Installation

 BINA
 
 BINA
 

HPCL VIZAG Refinery - Illinois Blower

 HPCL
 
 HPCL
 

CAIRN Energy - Surface Pumping System

 CAIRN
 
 CAIRN
 

GEECL CBM Compressor Skids

 GEECL
 
 GEECL
 

Guillotine Shear Project Bhilai Steel Plant

 Bhilai
 
 Bhilai
 
SAIL
MAHA VITARAN
INDIAN OIL
SAIL
MAHA VITARAN
INDIAN OIL
 

© Empire Mumbai. All rights reserved | Website by NWDCo